- Site scrape has been confirmed for 5.9, so in two days
- Slab will go down on 17.9
- Frame will commence 19.9
- Brickies have been booked
- Windows and frames have been ordered
Yay! We are getting there! So by the first week of October we should have the full frame up!
We did have one setback today though, the range hood that I loved is now discontinue :( but the replacement ones looks very similar and is a better model :) so that was a win for us :)
We also have a toilet now too :) Ah the trivial things...
We also have a toilet now too :) Ah the trivial things...
No comments:
Post a Comment