Sunday 9 February 2014

PCI

We had our PCI on Friday of last week, the 8th of Feb, with handover hopefull this Thursday 13th Feb (so long as our bank is organised!)

There were no major dramas with our house, we have been addressing them along the way and they have been fixed along the way.

There were many paint touch ups, as well as wall clean ups, so lots of post it notes. The other things were:

  • tile chipped in ensuite
  • basin not centered in bathroom
  • mortar a different colour under bathroom window
  • pencil marks on floor where the bolero was measured up
  • garage floor to be cleaned of paint spills and concrete blobs
we were also concerned re an obvious line in the carpet, but our supervisor assured us that this would go down over time. 

So all in all we were pretty happy with things. 

Looking forward to getting the keys and starting to move in from this week. Though the removalist wont come for a few more weeks as we want to get the shed and the drive way/crossover done first. Otherwise we would have a heck of a lot of mess in our new home!

2 comments:

  1. Hi Suzy and Nathan,
    Great blog, lots of detail. We are in the process of signing up for a Drysdale 30 in Traralgon at the moment and were wondering if there was anything in the build that you might have done differently now that you have been in your home for a few months.
    Regards,
    Alan and Denise

    ReplyDelete
  2. Hi Alan and Denise
    Apologies if this has sent twice, it looked the the first time i sent it failed

    The only thing I would change is putting the bolero floorboards in the rumpus room instead of carpet. But that's about it :)

    ReplyDelete